PROJECT DESCRIPTION
The objective of the project is to replace/rehabilitate four segments of San Andreas Pipeline No. 2 approximately 6,500 feet in four segments, from Harry Tracy Water Treatment Plant to the Golden Gate National Cemetery in San Bruno. The work is to be performed in San Mateo County, California.
For additional information about this project, please visit the SFPUC's website. To review the plans and specifications for the project, feel free to visit the Center's plan room at 150 Executive Park Blvd., Suite 1300, San Francisco, CA 94134
ENGINEER'S ESTIMATE
$21.7M
LBE REQUIREMENT:
20%
ONLY San Francisco (Local) Small & Micro-LBEs can be utilized to meet this requirement (Firms certified by SF Contract Monitoring Division). SFPUC-LBEs cannot be utilized to meet the 20% LBE Subcontracting Participation Requirement.
BID DATE:
December 07, 2017