Sewer Connection Permit Application

  • A Sewer Connection Permit Application must be submitted for any customers that need to establish or replace a sewer connection, e.g. for a new property, new development, or redevelopment with additional connections, a change in capacity charge, upsizing a sewer lateral, or lower lateral repair.
  • In addition to this permit, Applicant must acquire all necessary DBI permits and approvals, and pay any required SFPUC Water and Wastewater Capacity Charge fees due.

Part 1: Applying for Service

APPLICATION PROCESSING TIME

  • Application Review is expected to take 2 to 3 weeks.
    1. Application - Applicants can either fill out an application online and email the completed form to sewerinspections@sfwater.org or pick up a printed copy at SFPUC 5th Floor Counter at Department of Building Inspection (1660 Mission St) and mail to Sewer Inspection, 3801 Third St, Ste 600, San Francisco, CA 94124.

    2. Construction Plans and Drawings - As described in the Application, Applicant must provide Plan and Profile view drawings. SFPUC’s standard details can be accessed by clicking here.

    3. Review - SFPUC will review the Application to assess proposed impact to the collection system, limitations of the local sewers, and compliance with sewer lateral standard details and specifications. If needed, information will be transmitted to the Applicant regarding these review items.

    4. Application Approval - Upon completing internal Application review, a permit will be issued to the Applicant by email and/or mail.

    Part 2: Construction & Inspection
    1. Notification of Modifications – If there are any changes to site plans or application details, Applicant or Applicant's Contractor must notify SFPUC at least one week in advance of intended construction through the SFPUC Collection Systems Division phone line (415) 695-7321 and sewerinspections@sfwater.org.

    2. Inspection Scheduling – Applicant or Applicant’s Contractor schedules an inspection 72 hours in advance via the contact information above. Contractor also notifies San Francisco Public Works BSM.

    3. Installation and Connection – Applicant or Applicant’s Contractor installs sewer lateral and connects to SFPUC sewer main.

    4. Inspection – SFPUC conducts inspection with Applicant’s Contractor and determines if sewer lateral details and specifications are met. If they are not met, Contractor shall correct work, potentially accompanied by a follow-up inspection, or can request a variance.

    5. Permit Closure – For approved inspections, a copy of the completed application with SFPUC sign-off will be returned to Applicant to close the permit.

     

    If you have any questions regarding the above information or filling out the application, please contact:

     

    Collection System Division
    sewerinspections@sfwater.org
    (415) 695-7321

    or by mail:

    Sewer Inspection
    3801 Third Street, Ste 600
    San Francisco, CA 94124

    Last updated: 9/18/2018 4:42:08 PM