Bid Details
WW-628
Southeast Plant New Headworks Construction – Scope III Bid Solicitation 6

Bid due

09/24/2020
2:00 PM

  • Type Construction
  • Department Infrastructure
BACK TO CONTRACTS & BIDS LIST
Project Description
While information may be periodically added to this Project Description page, it exists only as a courtesy. Please only rely on official updates provided by Sundt-Walsh and on Sundt-Walsh's SmartBid website: https://secure.smartbidnet.com/LAPW

Subject to conditions prescribed by the City and County of San Francisco, CA responses to this bid request are sought from subcontractors for HVAC, Ductwork, and Demo. 

PROJECT DESCRIPTION:
The intent of this project is to replace the existing Headworks Facility at the SE Water Pollution Control Plant with a new all-weather 250 MGD Headworks Facility. This is solicitation 6 for Scope III New Headworks Construction. 

SCOPE / DRAWINGS: 
The drawings for Scope III are included in the Plan Room on Smartbidnet.com. The scopes being sought for this project are as follows:

3-39 HVAC and Ductwork - 20% LBE Requirement 
3-18 Final Demolition - 20% LBE Requirement

PRE-QUALIFICATION OF PROSPECTIVE SUBCONTRACTORS: 
The Owner has determined that subcontractors who submit bids to Sundt/Walsh on this Project must be pre-qualified. Those subcontractors who pre-qualify will be allowed to bid on the above Scope of Work. Interested firms may obtain Pre-qualification Documents on the Smartbidnet.com website or by contacting David Cooley, via e-mail at dcooley@sundt.com. All prequal documentation must be submitted by September 25, 2020. 

LOCAL BUSINESS ENTERPRISE (LBE) REQUIREMENTS: 
The following project-wide LBE participation requirement is: LBE-15%. Each Bid Package has a specific LBE requirement as indicated above. Any proposals that fail to meet the Bid Package LBE requirement will be deemed non-responsive.

DISADVANTAGED BUSINESS ENTERPRISE (DBE) REQUIREMENTS: 
All subcontractors are hereby notified that it is expected that work to be performed under this contract will be in full or in part financed by the Clean Water State Revolving Fund (SRF), administered by the United States Environmental Protection Agency (US EPA) and the State Water Resources Control Board (SWRCB). Bidders shall comply with all applicable terms and conditions, special provisions, and reporting requirements, as set forth in these specifications, and as may be required by federal law, rule, or regulation. Additionally, meeting the project-wide Fair Share Objective is encouraged: MBE-6.4%, WBE-2.0%. Refer to Contract Section 00 48 10.01, Paragraph 2 for more information.

QUESTIONS: 
Direct all project specific questions to David Cooley at Sundt/Walsh. All questions should be submitted via e-mail. The e-mail address is Dcooley@sundt.com.

Request for proposal

  • ESTIMATED COST
    Varies
  • DUE DATE
    09/24/2020
  • DUE TIME
    2:00 PM
  • DURATION
    Varies
  • LOCATION
  • CONTACT
    David Cooley dcooley@sundt.com

Pre-Bid Conference

  • DATE
    09/02/2020
  • TIME
    2:00 PM
  • ATTENDANCE
    Not Mandatory
  • LOCATION
    Please email David Cooley, dcooley@sundt.com, if you would like to attend.
  • ADVERTISEMENT DATE
    08/20/2020
LIST OF CERTIFIED LBE FIRMS AT HRC WEBSITE