Advanced Search   
SFPUC Home   |   SFPUC Site Index   |   Calendar of Events   |   Contact Us   

Construction in Your Neighborhood

Is the San Francisco Public Utilities Commission (SFPUC) working in your area?

The following is a list of construction projects in San Francisco and other Bay Area regions that may affect your neighborhood. Click on Peninsula projects or East Bay projects or Central Valley projects for more information.

District 2District 3District 1District 5District 6District 4District 8District 7District 9District 10District 11District 6


Click on a
SUPERVISORIAL DISTRICT above to review construction in your area.
Areas outside of San Francisco are linked below.


DISTRICT 1

There are currently no projects in this area.

Back to Top


DISTRICT 2

COW HOLLOW/PACIFIC HEIGHTS

Water main construction on Pacific Avenue from Pierce to Scott streets

Starting the first week of June, the contractor starts saw-cutting, trenching and installing 24-inch transmission line through next week. The removal of abandoned railway track on this block continues.

Work at other locations next week:
1. Scott and Clay: Sewer replacement work begins this week involving saw cutting, excavate trench and construct new manhole
2. Vallejo at Franklin: Puts 24-inch water transmission line into the ground
3. Vallejo at Van Ness: Installs 36-inch casing.
4. Vallejo/ Gough & Octavia: No work for the next two weeks
Parking and Traffic: Pacific Avenue between Pierce and Scott streets is close to through traffic but garage access for residents is maintained at all times. If there is no construction by noon, public parking is allowed. Please allow extra time in case of traffic delays during construction hours.

Work Hours: Monday to Friday 8 a.m. to 6 p.m. Monday to Friday.

Contact: Ben Chan bychan@sfwater.org or call 415-554-3284, or cell 415-306-4592. After hours and weekends call 415-550-4911.

Back to Top



DISTRICT 4

SUNSET DISTRICT 

Oceanside Wastewater Treatment Plant Aging Infrastructure Project (Ventilation Improvements)

The construction work for this project is expected to be completed in Summer 2009.  The project will replace the ventilation system and improve treatment processes at the Oceanside Wastewater Treatment Plant.

For more information, contact Idil Bereket at (415) 554-0741 or ibereket@sfwater.org.
AFTER HOURS EMERGENCY: (415) 242-2238


Back to Top


DISTRICT 5

WESTERN ADDITION 

Turk Street Water Main Replacement Project (between Fillmore and Divisadero)

Project has reached substantial completion.  Contractor will pave on McAllister the week of June 8th.

Work Hours: Monday to Friday 7 a.m. to 5 p.m.

Parking and Traffic: Parking restriction signs are posted in the affected area. Please see signs for details.

Contact: Ben Chan bychan@sfwater.org or call 415-554-3284.

Back to Top


DISTRICT 6

SOUTH OF MARKET

Channel Pump Station Odor Control and Facility Improvement Project

The construction work for this project began in September 2008 and is expected to be completed in December 2009. The project will reduce wastewater odors in the Mission Bay neighborhood and improve the reliability of the pump station.

For more information, contact Kenya Briggs at (415) 554-0715 or kbriggs@sfwater.org.
AFTER HOURS EMERGENCY: 415-648-6882, EXT. 1300 

TENDERLOIN

Jones Street (between Market & Greenwich) Water Main Replacement Project

Contractor is replacing water mains along Jones Street between Market & Greenwich Streets. Crews are currently working between Ellis & Sutter.

The project is expected to be completed by the end of October 2009.

Work Hours: Monday to Friday 8 a.m. to 5 p.m.

Parking and Traffic: Parking restriction signs are posted in the affected area. Please see signs for details. If no construction takes place by noon, public parking is permitted.

For more information, contact Robert Lopez at (415) 554-3286 or rlopez@sfwater.org.  After hours and weekends call 415-550-4911


Back to Top


DISTRICT 7

MIRALOMA / MOUNT DAVIDSON 

Mt. Davidson Tank (Atop Mt. Davidson)

Work continues near La Bica & Myra and at Dalewood.

This project is upgrading an aging water storage tank and recently added new water pipeline. Most trails on Mt. Davidson are reopened after temporary closures in the Fall. Construction work is taking place at the top of the mountain.  Project completion expected in early 2010.

Contact: 415-551-4659, after hours and weekends call 415-550-4911.

Mt. Davidson Pump Station (Agua Way near Chaves Avenue)

Neighbors will experience some noise and dust during the rebuild of the pump station. Completion expected in early 2010.

Contact: 415-551-4659, after hours and weekends call 415-550-4911.

Stanford Heights Reservoir (near the intersection of Teresita and Agua Way)

This project is more than half-way complete! The east basin of this reservoir is undergoing a seismic retrofit. Some pipeline work in the streets can be expected. Completion anticipated in late 2009.

Work hours: 7:00 a.m. to 5:00 p.m. Monday through Friday with occasional Saturday work inside the reservoir.

Contact: 415-551-4659, after hours and weekends call 415-550-4911.


TWIN PEAKS / CLARENDON AVENUE

Forest Knolls Pump Station (Clarendon Ave, Christopher and Forest Knolls)

Contractor is working on electrical and mechanical setup inside the building and fence installation. This project will be finished in mid 2009.

Work hours are Monday through Friday from 7:00 a.m. to 5:00 p.m.

Contact: 415-554-3244, after hours and weekends call 415-550-4911. Check out our blog: sfwater.org/district7


Back to Top


DISTRICT 8

UPPER MARKET/NOE VALLEY/CASTRO

Noe Valley Transmission Main Improvements

For updates and comments, go to sfwater.org/district8 blog.

Vista Francisco Pump Station Upgrade Project (Crestline Drive near Burnett Avenue)

The construction contract has been awarded for this project and the contractor is anticipating starting construction in July.

For more information, contact Robert Lopez at (415) 554-3286 or rlopez@sfwater.org

Back to Top


DISTRICT 9

BERNAL HEIGHTS

Water Main replacement at Coso, Prospect, Stoneman, Manchester, Folsom, Ripley streets, and Holladay Avenue


This project has reached substantial completion.  Paving will be completed the week of June 8th.

Contact : Ben Chan bychan@sfwater.org call 415-554-3284. 
 
Water Main replacement On Crescent, Benton, Arnold, Roche, Roscoe, Porter

CDD continues to replace water mains along Crescent Avenue between Mission & Andover Streets.  Currently crews are working near Arnold, Benton and Porter.
   
Work Hours : Monday to Friday 7 a.m. to 5 p.m.

Trafiic and Parking : Parking restriction signs will be posted in the affected area. Please see signs for details.  If no construction takes place by noon, public parking is permitted.  

For more information, contact Robert Lopez at (415) 554-3286 or rlopez@sfwater.org.  After hours and weekends call 415-550-4911 

Back to Top


DISTRICT 10

PORTOLA DISTRICT 

Alemany Pump Station (Felton & Dartmouth)

Crews continue work and are currently on schedule to meet the projected completion date. The target completion date for this project is Winter 2009.

Restrictions in the area will be posted in advance. Parking will temporarily removed in the construction area. Please see signs for exact details.

For more information, contact Robert Lopez at (415) 554-3286 or rlopez@sfwater.org.  After hours and weekends call 415-550-4911


BAYVIEW DISTRICT

Water Main replacement on Jennings, Le Conte and Key

CDD are replacing water mains along Jennings, Le Conte and Key Avenue.  Currently crews are working on Le Conte.
   
Work Hours : Monday to Friday 7 a.m. to 5 p.m.

Trafiic and Parking : Parking restriction signs will be posted in the affected area. Please see signs for details.

If no construction takes place by noon, public parking is permitted.  

For more information, contact Robert Lopez at (415) 554-3286 or rlopez@sfwater.org.  After hours and weekends call 415-550-4911

Southeast Wastewater Treatment Plant Digester Odor Improvement
The construction work for this project began in Summer 2007 and is expected to be completed in Fall 2008. This project will reduce wastewater odors in the Bayview District and maximize energy reuse at the wastewater treatment plant.

For more information, contact Idil Bereket at (415) 554-0741 or ibereket@sfwater.org. AFTER HOURS EMERGENCY: 415-648-6882, EXT. 1300

Back to Top


DISTRICT 11


Back to Top


PENINSULA

SOUTH SAN FRANCISCO 

Baden Valve Lot Improvement (El Camino Real and West Orange Avenue)

Construction related noise will be minimal and no interruption of water service in this final upgrade phase.

Work hours: Monday through Friday from 7:00 a.m. to 5:00 p.m.

Contact: Jim Chien jchien@sfwater.org or call 415-554-3244. After hours and weekends call 650-872-5900


MILLBRAE / SAN BRUNO
 

Harry Tracy Water Treatment Plant Short-Term – Crystal Springs Road@ Highway 280 

Construction is ongoing at the plant. There will be no impact to water service and pedestrians and horse stables in the area. However, residents can expected to see trucks travel on Crystal Springs Road during regular construction days and hours. We have asked the contractor to use caution when driving near the San Bruno Senior Center and the Crystal Springs Terrace Apartments.

Work hours: Monday through Friday from 7:00 a.m. to 5:00 p.m.
Contact: Jim Chien, Jchien@sfwater.org, (415) 554-3244 or after hours/weekends call (650) 872-5900.

Back to Top


EAST BAY

There are currently no projects in this area.

Back to Top


CENTRAL VALLEY

There are currently no projects in this area.

Back to Top







 
 
Visit sfgov.org the official site of the City and County of San Francisco
Copyright © 2009, San Francisco Public Utilities Commission

Privacy Policy  |   SFPUC Home  |   Site Index  |   Contact Us  |   Newsletter  |   RSS feed