In 2005, the San Francisco Public Utilities Commission (SFPUC) launched a citywide $150 million 5-Year Wastewater Capital Improvement Program (5-Yr WWCIP) to improve the reliability and efficiency of San Francisco’s combined wastewater and storm water system. Over the next few years these projects will help address the most critical needs of our aging wastewater system, improving the capacity of sewer mains, upgrading treatment facilities and reducing wastewater odors.
The 5-Yr WWCIP was made possible through the 2005 wastewater service charge increases. The additional funding also allowed us to increase the numbers of sewers replaced on an annual basis and improve the operations at our wastewater treatment plants. For more information on the 5-Year WWCIP, please contact Idil Bereket, SFPUC Communications at (415) 554-0741 or ibereket@sfwater.org.
Serious short-term critical needs are being addressed, but more needs to be done. In 2006, the SFPUC launched the S.F. Sewer System Master Plan to look at the long-term needs of the entire wastewater system. Visit www.sfsewers.org for more information.
The following projects have been completed:
- Cayuga “North” Sewer Improvement Phase I
- Monterey Boulevard/Baden Street/Circular Avenue Sewer Improvement
- Mission Street/Foote Avenue Sewer Improvement
- Vicente Street Sewer Improvement Phase I
- Teresita Boulevard “South” Sewer Improvement
- Shotwell Street/18th Street Drainage Improvement
- Vicente Street Sewer Improvement Phase II
- Justin Dr./Marrietta St./Del Vale Ave. Sewer Improvement
- Griffith Street Pump Station Odor Improvement
- Embarcadero Vent Elements Odor Improvement Phase I
- Southeast Wastewater Treatment Plant Aging Infrastructure Project (Aeration Basin Mixer)
- Southeast Wastewater Treatment Plant Aging Infrastructure Project (Secondary Clarifier Coating)
- Oceanside Wastewater Treatment Plant Aging Infrastructure Project (Westside Pump Station Bar Screen)
- Westside Pump Station Aging Infrastructure Project (Lift Pump Replacement)
The following sewer improvement/aging infrastructure projects are currently under construction:
- Mission Street / Mount Vernon Avenue Sewer Improvement
- Southeast Wastewater Treatment Plant Digester Odor Improvement
- Brotherhood Way/St. Charles Avenue Sewer Improvement
- Oceanside Wastewater Treatment Plant Aging Infrastructure Project (Ventilation Improvements)
- Phelps St/Topeka Ave/Pomona St. Sewer Improvement
Projects scheduled to break ground in 2008:
- Channel Pump Station Improvements Project
- Southeast Wastewater Treatment Plant Building 010 (Headworks) Odor Control Improvements
- Southeast Wastewater Treatment Plant Gas Handling Improvements - Phase 2