Skip to page body Home Customer Service How To Environment Projects & Programs About Us

Calaveras Dam Replacement Project

Project Information
Construction
Start
August 2011
Construction
Finish
Mid 2019
Cost $810 Million
Project Phase Construction
Additional Information

The information shown reflects the current forecast information published in the latest WSIP Quarterly Report.

Project Materials

Project Factsheet - Fall 2016
Spillway Media Fact Sheet

Naturally Occurring Asbestos Information and Data

Naturally Occurring Asbestos Questions and Answers
Air Monitoring Results

 

Environmental Impact Report

Volume 1      • Volume 5-6
Volume 2      • Volume 5-7
Volume 3      • Volume 5-8
Volume 4      • Volume 6
Volume 5-1   • Addendum 1
Volume 5-2   • Addendum 2
Volume 5-3   • Addendum 3
Volume 5-4  
Volume 5-5  

Summary Data Reports from
Air Monitoring Events

August 2008 through August 2009
September 2009 through July 2010
August 2010 through November 2010

 

Need more information? Contact:

Maria Le
Phone: 925.493.4535
Email: mle@sfwater.org

Betsy L. Rhodes
Phone: 415.554.3240
Email: blauppe@sfwater.org

Sign up for our Sunol Valley Regional Blog to follow the projects in that area.

SUBSCRIBE TO OUR BLOG
Blogger

CDRP

Calaveras Road Closure

July 5, 2016 through December 31, 2017

Calaveras Road between Geary Road and Oakridge Road has been closed to vehicle, pedestrian, and bicycle traffic on weekdays for 18 months. This is due to large truck traffic on the narrow portions of Calaveras Road for dam construction. Calaveras Road opens Saturday mornings 6 a.m. and closes Sunday evenings at 11:00 p.m.

To stay updated, please join our road closure notification mailing list by emailing mle@sfwater.org  See the closure map and more details on the Calaveras Road closure at sfwater.org/CalaverasRoad

Project Description
The project consists of building a new zoned earth and rock fill dam immediately downstream of the existing dam. The replacement dam will have a structural height of 220-feet high and is designed to accommodate a maximum credible earthquake on the Calaveras Fault. The dam will have a crest length of 1,210 feet, a base thickness of 1,180 feet, and crest thickness of 80 feet. The total volume of the dam will be approximately 3.5 million cubic yards. The replacement dam will restore the original reservoir capacity of 96,850 acre-feet, or 31 billion gallons of water. The storage is crucial to providing adequate water to our 2.6 million customers in the Bay Area.

What's New at Calaveras Dam?

Construction began in 2011 to build a new earth and rock fill dam adjacent to the existing dam. To date, the Contractor has moved over six million cubic yards of earth and rock materials and started to construct the new dam. Crews have constructed a new shaft and five adits (tunnels) which connect outlet pipelines to the reservoir. We have completed grouting operations on the right abutment and continue grouting on the left abutment. The new spillway was completed in Spring 2016. A new 78 inch diameter pipe has been installed and encased in concrete, which will be connected to existing lines to deliver water. Dam embankment work is scheduled to begin in late 2016. As of August 2016, the project is over 77% complete.

Construction team standing in the newly completed dam spillway 

Team members celebrate completion of the new spillway in April 2016

Check out our time lapse video of our construction progress.

Last updated: 9/7/2016 3:05:10 PM