Pre-Qualification for Select SFPUC Construction Projects
Published: 01/07/2008  |  Updated: 01/16/2008
Published By: Contract Administration Bureau

The SFPUC has implemented a pre-qualification program to determine bidder responsibility prior to submission of bids for select projects. Bidders for designated construction projects must be pre-qualified prior to submitting bids. It is mandatory that all Licensed Contractors who intend to submit bids for these designated projects, fully complete the Pre-Qualification Questionnaire: Request for Qualifications - Parts I, II, and III as well as the Technical Requirements: Request for Qualifications - Part IV for the applicable project category(s) provide all materials requested herein, and be approved by SFPUC as a qualified bidder.

Pre-qualification application packages may be submitted at any time throughout the year. The SFPUC requires a minimum of 30 days to process a pre-qualification application following submittal of all required documents, including timely receipt of Reference Questionnaires. Notice of “Qualified Contractors” will be posted on the SFPUC website (www.sfwater.org) and will be updated on the 1st and 15th of each month. Pre-Qualification approval will remain valid for two (2) calendar years from the posted approval date.

Request for Qualifications Parts I, II, and III

For Technical Requirements: Request For Qualifications (RFQ) Part IV, see the respective link under each Project Category below. Please be advised that Estimated Advertisement Dates and Estimated Contract Values may be subject to change. Contractors are advised to check this webpage regularly for updates.

SFPUC Wastewater Projects

Estimated Contract Value*

Estimated Advertisement Date*

SEWER PIPELINES

RFQ Part IV - Sewer PL

   

Staples/Hazelwood/Montecito Sewer Improvement

$5-$10M

January 2008

Cesar Chavez Sewer Improvement, Phase 1

$5-$10M

January 2008

Ocean Ave Sewer Improvement

$5-$10M

March 2008

Sunnydale Auxiliary Sewer

$10-$25M

March 2008

Alemany & Sickles Sewer Improvement

$1-$10M

May 2008

     

WASTEWATER TREATMENT FACILITIES

RFQ Part IV - WWTrtmt

   

Major Mechanical and Electrical Equipment Replacement

$1-$10M

March 2008

SEP 010 Odor Control

$1-$10M

May 2008

OSP Digester Mixing Improvements

$1-$10M

January 2009

     

WASTEWATER PUMP STATIONS

RFQ Part IV - WWPS

   

Tennessee Pump Station Phase I

$1-$10M

March 2008

Chemical Feed Systems Phase II

$1-$10M

March 2008

Embarcadero Box Hydraulic Modifications

$1-$10M

April 2008

SWOO Cleaning and Backflow Prevention

$1-$10M

April 2008

Tennessee Pump Station Phase II

$1-$10M

November 2008




SFPUC Local Water Projects

Estimated Contract Value*

Estimated Advertisement Date*

SMALL (< 48 “) WATER PIPELINES

RFQ Part IV - Less48PL

   

North University Mound System Upgrade

$12M

February 2008

Noe Valley Transmission Main, Phase 2

$8M

July 2008

San Andreas Pipeline No. 3 Installation

$30M

March 2009

City Distribution Division - Ductile Iron Main Replacement

$1 - $3M

Approx. 6 per year

     

WATER PUMP STATIONS AND TANKS

RFQ Part IV - LWPS/T

   

Mount Davidson Pump Station and Storage Tank Upgrades

$5M

January 2008

Vista Francisco Pump Station Upgrades

$4M

July 2008

Lake Merced Pump Station Essential Upgrades

$57M

August 2008

La Grande Pump Station Upgrades

$4M

March 2009

Forest Hill Pump Station Upgrades

$4M

January 2010

     

WATER RESERVOIRS

RFQ Part IV - LWRSVR

   

University Mound Reservoir Upgrades – North Basin

$43M

June 2008

Sutro Reservoir Rehab & Seismic Upgrade

$30M

August 2009



SFPUC Regional Water Projects

Estimated Contract Value*

Estimated Advertisement Date*

WATER TUNNELS

RFQ Part IV - RWTunnels

   

New Crystal Springs Bypass Tunnel

$68M

June 2008

Bay Division Reliability Upgrade – Bay Tunnel

$269M

August 2008

     

LARGE (> 48”) PIPELINES

RFQ Part IV - Grtr48PL

   

Alameda Siphon # 4

$42M

June 2008

Bay Division Pipeline Reliability Upgrade- Pipeline

$184M

October 2008

Crystal Springs Pipeline No. 2 Replacement

$46M

July 2009

San Antonio Backup Pipeline

$16M

August 2009

San Joaquin Pipeline System

$200M

December 2010

     

VALVE LOTS

RFQ Part IV - RWVL

   

Baden and San Pedro Valve Lots Improvements

$21M

October 2008

BDPL No. 3 & 4 – Crossovers

$25M

October 2008

New San Joaquin Pipeline Crossovers

$10M

October 2009

     

WATER TREATMENT PLANTS

RFQ Part IV - RWTP

   

SVTWP Expansion & Treated Water Reservoir

$105M

April 2009

HTWTP Long-Term Improvements

$130M

October 2010

     

STRUCTURAL UPGRADES/RETROFITS

RFQ Part IV - RWStruct

   

San Antonio Pump Station Upgrade

$9M

December 2008

Pulgas Balancing Reservoir Rehabilitation

$13M

April 2009

Lower Crystal Springs Dam Improvements

$17M

July 2009

Pulgas Discharge Channel Modifications

$5M

October 2009



Stand Alone Regional Water Projects**

Estimated Contract Value*

Estimated Advertisement Date*

Calaveras Dam Replacement

$232M

September 2008

New Irvington Tunnel

$263M

June 2009

SCADA System

$11M

July 2009

Groundwater Sub-Project B – North Westside Basin Wells

$21M

March 2010

Crystal Springs/San Andreas Transmission Upgrade

$114M

April 2010

Recycled Water Project

$102M

May 2010

Watershed Environmental Improvement Program

$15M

July 2010

Groundwater Sub-Project C – Conjunctive Use

$26M

August 2010

Groundwater Sub-Project A – Lake Merced Water Levels

$10M

October 2010

Seismic Upgrade of BDPLS No. 3 & 4 @ Hayward Fault

$43M

December 2010

Alameda Creek Fishery Enhancement

$11M

April 2012


* Estimated Contract Values and Estimated Advertisement Dates may be subject to change.
**A separate pre-qualification process with project-specific Request for Qualifications will be conducted for each SFPUC Stand Alone Regional Water Project. Links to the RFQ will be issued 3-6 Months prior to the Estimated Advertisement Date.

Potential bidders are encouraged to submit pre-qualification packages as soon as possible, so that they may be notified of pre-qualification status well in advance of upcoming projects.

For listing of SFPUC approved pre-qualified contractors, click below:
SFPUC Pre-Qualified Contractors

For questions on pre-qualification, please send an email to: prequal@sfwater.org  or leave a voicemail at 415.551.4603.






 
 
Visit sfgov.org the official site of the City and County of San Francisco
Copyright © 2008, San Francisco Public Utilities Commission

Privacy Policy  |   SFPUC Home  |   Site Index  |   Contact: Email & Phone