Stanford Heights Reservoir Construction Update: Summer 2008
Published: 07/14/2008
| Updated: 10/02/2008
Published By: Communications and Public Outreach
Published By: Communications and Public Outreach
This summer, NTK Construction will perform additional street trench and pipe work on Agua Way. In July or August, they will remove equipment from the existing station, disconnect water pumps and demolish the building. This fall, electrical wires will be installed in the sidewalk on the reservoir side of Agua Way. The sidewalk will be temporarily closed at that time for safety reasons. The PG&E transformer at Teresita and Agua Way will be replaced with a newer, more efficient transformer.