| Pre-qualification |
| |
| The San Francisco Public Utilities Commission (SFPUC) is
undertaking a major water system improvement program to repair and improve the Hetch Hetchy
water delivery system. The SFPUC will let construction contracts valuing $2.3 billion, between now
and 2013, using a pre-qualification process to determine bidder responsibility prior to submission of bids.
Notice is hereby given on October 2, 2006, bidders for select SFPUC construction projects must be
pre-qualified prior to submitting bids for designated projects (pdf). |
| |
| Read more about the pre-qualification process >> |
| |
| |
| Contractor/Consultant Self Posting for LBE Opportunity Advertising |
| All bidders shall undertake good faith outreach as set forth in 14B.8(C) to select subcontractors to meet LBE goals. This site provides contractors and consultants an opportunity to submit a request for interest from HRC certified LBE subcontractors. By posting Prime Bidders' requests for subcontracting opportunities, PUC makes no representations to the reader that the listed Prime Bidders are qualified or authorized to advertise services as licensed contractors. If you are having problems posting a request for LBE opportunities, read the posting instructions.
| |
| |
| Details |
Documents |
Contractors' list |
Number |
Title |
Posted |
Modified |
Bid due |
LBE Bid Requests |
|
 |
 |
 |
WD-2543 |
North University Mound System Upgrade-Water Main installation, Sewer Replacement & Pavement |
6/17/08
|
7/1/08
|
7/24/2008 |
2 |
 |
 |
 |
HH-933 |
SFPUC Efficient Lighting for18 Port of San Francisco Facilities |
6/16/08
|
7/2/08
|
7/17/2008 |
1 |
 |
 |
 |
WD-2498 |
New Crystal Springs Bypass (Polhemus) Tunnel |
6/11/08
|
7/2/08
|
7/31/2008 |
|
 |
 |
 |
WW-450R |
Channel Pump Station Odor Control and Facility Improvements - BID RESULT |
5/28/08
|
7/3/08
|
7/3/2008 |
7 |
 |
 |
 |
WW-463 |
SEWPCP Gas Handling Improvements Phase II - BID RESULT |
5/21/08
|
6/12/08
|
6/12/2008 |
4 |
 |
 |
 |
WW-473 |
Sanchez/Noe/Ford Streets Sewer Replacement - BID RESULT |
5/8/08
|
6/6/08
|
6/5/2008 |
10 |
 |
 |
 |
WW-477 |
Job Order Contract, Spot Sewer Repair (A-license), San Francisco - BID RESULT |
4/28/08
|
6/12/08
|
6/12/2008 |
7 |
 |
 |
 |
WW-476 |
Job Order Contract, Spot Sewer Repair (A License) San Francisco - BID RESULT |
4/28/08
|
6/6/08
|
6/5/2008 |
7 |
 |
 |
 |
WD-2564 |
Harry Tracy Water Treatment Plant Short Term Improvement Phase 2&3 - BID RESULT |
4/7/08
|
5/16/08
|
5/15/2008 |
3 |
 |
 |
 |
WD-2461 |
8-inch DIP Main Installation in Turk, McAllister, Pierce & Seymour Streets - BID RESULT |
4/1/08
|
4/25/08
|
4/24/2008 |
5 |
 |
 |
 |
WD-2576 |
CDD As-Needed 2008/2009 Annual Paving Contract #2 - BID RESULT |
3/25/08
|
5/6/08
|
5/1/2008 |
|
 |
 |
 |
WD-2569 |
CDD As Needed 2008/2009 Annual Paving Contract #1 - BID RESULT |
3/17/08
|
4/18/08
|
4/17/2008 |
1 |
 |
 |
 |
WW-427 |
Dartmouth/Gates/Murray Sts & Richland/Wide Ave Sewer Replacement - BID RESULT |
3/7/08
|
4/4/08
|
4/3/2008 |
8 |
 |
 |
 |
HH-929 |
Job Order Contract, Lighting Efficiency & Upgrade Service for SF/Penisula Areas - BID RESULT |
3/4/08
|
4/25/08
|
4/24/2008 |
8 |
 |
 |
 |
HH-928 |
Job Order Contract, Lighting Efficiency & Upgrade Service for SF/Penisula Areas - BID RESULT |
3/4/08
|
4/22/08
|
4/17/2008 |
7 |
 |
 |
 |
HH-927 |
Job Order Contract, Lighting Efficiency & Upgrade Service for SF/Penisula Areas - BID RESULT |
3/4/08
|
4/16/08
|
4/10/2008 |
5 |
 |
 |
 |
WW-466 |
Sewer Inspection/Sewer Cleaning/Easement Sewer Sealing - BID RESULT |
3/4/08
|
4/14/08
|
4/10/2008 |
4 |
 |
 |
 |
WW-429 |
Claremont Blvd/Edna St/Naglee & Oneida Ave Sewer Replacement - BID RESULT |
2/25/08
|
3/28/08
|
3/27/2008 |
10 |
|
 |