| On Line Bids and RFPs View Details for Construction Management Services for WSIP - New Crystal Springs Bypass Tunnel Project |
| Bid Type: | Professional Services | ||
| Bid number: | CS-912 | ||
| Bid title: | Construction Management Services for WSIP - New Crystal Springs Bypass Tunnel Project | ||
| Department: | CMB | ||
| Description: | The San Francisco Public Utilities Commission (SFPUC), a department of the City and County of San Francisco (“City”) seeks to retain the services of a qualified Proposer to assist the SFPUC with the Construction Management of the New Crystal Springs Bypass Tunnel Project (NCSBTP). The successful Proposer will become the NCSBTP Consultant Construction Manager (CCM) and will be required to provide fully qualified and highly experienced construction management personnel to manage the construction of the project ***** February 7, 2008 added Professional Services Checklist ****** February 20, 2008 added addendum #1 to extend the deadline for reserving a space on the site visit ****** February 21, 2008 added Pre-submittal sign-in sheet ***** ___________________________________________________________ February 29, 2008 added Q&A's and Cal OSHA Classification ___________________________________________________________ March 4, 2008 added Addendum#2 and Geotechnical Report ___________________________________________________________ March 5, 2008 added Addendum #3 to add Adminstrative DEIR web link ___________________________________________________________ March 17, 2008 added Addendum #4 to change oral interview date and update section on Waiver for Release of Liability ___________________________________________________________ April 15, 2008, the written evaluation has concluded with short-listed firms as follows: 1) Jacobs and Associates Inc., and 2) Dr. G Sauer Corporation (DSC) and Cooper Pugeda Management, Inc. (CPM) a Joint Venture. ___________________________________________________________ The selection process concluded with the final ranking as follows: Rank 1: Jacobs and Associates Inc., and Rank 2: Dr. G Sauer Corporation (DSC) and Cooper Pugeda Management, Inc. (CPM) a Joint Venture. The recommendation to award the contract is scheduled to go before the SFPUC on May 27, 2008. ___________________________________________________________ |
||
| Estimated cost: | $9,000,000.00 | Bid date due: | 3/19/2008 | Bid time due: | 1:00 PM | Duration: | 42 Months | Location: | 1155 Market Street, 9th Floor San Francisco, CA |
| Contact: | Contract Services | Contact telephone: | (415) 934-5732 |
| Contact email: | rfp@sfwater.org | ||
| Pre-bid Conference Date: | 2/21/2008 | Pre-bid conference time: | 10:00 AM | Pre-bid Requirement of HRC Good Faith Effort: | Yes | Pre-bid conference location: | State Building - 455 Golden Gate Avenue San Francisco, CA |