The San Francisco Public Utilities Commission (SFPUC), a department of the City and County of San Francisco (“City”) seeks to retain the services of a qualified Proposer to assist the SFPUC with the Construction Management of the Seismic Upgrade of the Bay Division Pipeline (BDPL) Nos. 3 & 4 at Hayward Fault Project. The successful Proposer will become the Seismic Upgrade of BDPL Nos. 3 & 4 at Hayward Fault Project Consultant Construction Manager (CCM) and will be required to provide fully qualified and highly experienced construction management personnel to assist the SFPUC to manage the construction of the project.
The Local Business Enterprise (LBE) rating bonus provisions of Chapter 14B shall apply to this project. In addition, the LBE subconsulting goal for this project is 18% of the total value of the goods and/or services to be provided. Please contact Andrew Houston, HRC Contract Compliance Officer at (415) 551-4335 for all HRC related issues.
2/22/2012: Addendum 1 Posted
2/24/2012: Pre Submittal Meeting Sign In Sheet
3/9/2012: Addendum 2 Posted. NOTE: Bid Due Date has changed to March 19th
3/12/2012: Addendum 3 Posted.
3/12/2012: Questions & Responses Posted.
05/24/2012: The evaluation process is complete with EPC Consultants Inc. as the highest ranked Proposer.