Advanced Search   
SFPUC Home   |   Site Index   |   Contact: Email & Phone   




Project: Pulgas Balancing Reservoir Rehabilitation Projects

Project–At–A–Glance

WSIP Region:            
Peninsula

Location
Unincorporated
San Mateo County

Construction Start
September, 2005 (First Project)

Construction Finish
May, 2013 (Last Project)

Current Status
Planning, Design, Construction, Environmental

The Pulgas Balancing Reservoir is seismically vulnerable, requires improvements to sanitary protections, and requires general rehabilitation of miscellaneous structural, mechanical and electrical systems. A general condition assessment was conducted that documented areas of general structural deterioration on the interior of the reservoir. The project is provided in response to the Water Quality and Delivery Reliability level of service goals.The original project has been divided into five separate projects to address required improvements and to facilitate construction. To date, two of the five projects have been completed. The remaining projects to be completed are:

Discharge Channel Modifications

Description
The discharge channel modifications would increase the channel’s capacity to 250 million gallons a day (mgd).  Project components would include raising the channel walls, repairing concrete cracks and exposed reinforcing steel, strengthening and interconnecting the channel floor sections, and strengthening the tall tapered wall near the Pulgas Tunnel.

Construction Start: May, 2009
Construction Finish: January, 2011
Project Phase: Design, Environmental
Project Cost: $9M

Structural Rehabilitation and Roof Replacement

Description
The project would include structural rehabilitation of the reservoir.  This would consist of seismic retrofit of the walls, installation of a new steel frame roof, and repair of concrete cracks and exposed reinforcing steel. The general rehabilitation would also include installing a new ventilation system and sampling ports, replacing utility piping, and upgrading the electrical system.

Construction Start: October, 2009
Construction Finish: May, 2013
Project Phase: Design, Environmental
Project Cost: $31M

Modification of Existing Dechloramination Facility

Description
Improvements to the dechloramination and pH control facilities are necessary to address immediate compliance issues. The necessary modifications are still under evaluation; therefore the specific scope of work has not been identified. The modifications are anticipated to primarily be made to the flow measurement and control system, and to the various process control and chemical feed systems. Emphasis will be placed on chlorine removal and pH adjustment first to comply with existing regulations, with consideration towards the interdependent secondary goal of maximizing ammonia removal.

Construction Start: July, 2010
Construction Finish: November, 2011
Project Phase: Planning, Environmental
Project Cost: $9M

Inlet/Outlet Work
Project Completed:    May, 2006

Description
The project provided new inlet and outlet piping promote better water mixing. The shutdowns associated with construction of these improvements also provided an opportunity to perform a condition assessment of the reservoir interior that has been used to help identify work associated with the Structural Rehabilitation and Roof Replacement Project.

Project Complete: May, 2006
Project Cost: $2M

Note: Schedule and cost information shown may vary from the 2007 Approved WSIP Schedule and Budget. The information shown reflects the current forecast information published in the latest WSIP Quarterly Report.

Need more information?
Contact Maureen Barry at (415) 554-3297 or via email at mbarry@sfwater.org





 
 
Visit sfgov.org the official site of the City and County of San Francisco
Copyright © 2009, San Francisco Public Utilities Commission

Privacy Policy  |   SFPUC Home  |   Site Index  |   Contact: Email & Phone