Project: North University Mound System Upgrade

Project–At–A–Glance

WSIP Region
San Francisco Local

Construction Start
November, 2008

Construction Finish
July, 2010

Current Status
Construction

Project Cost
$14M

This project is in the final stages of design and is anticipated to be advertised to qualified contractors in summer 2008 with construction anticipated to begin fall 2008.  This project will address supply issues associated with the University Mound (UM) system. The UM system and the Sunset Supply system are two independent systems now.Under this project they will be tied together to provide water to downtown areas in case of emergencies.

Project Background:
The San Francisco Public Utilities Commission (SFPUC) plans to upgrade the City’s water distribution system by connecting a distribution zone in the east to distribution zone in the west with the installation of a new transmission main in parts of North Beach, Russian Hill, Pacific Heights and Cow Hollow Neighborhoods beginning in summer 2008.  In addition some water & sewer mains and other system components will be replaced. 

Need more information?
Contact Maureen Barry at (415) 554-3297 or via email at mbarry@sfwater.org





 
 
Visit sfgov.org the official site of the City and County of San Francisco
Copyright © 2008, San Francisco Public Utilities Commission

Privacy Policy  |   SFPUC Home  |   Site Index  |   Contact: Email & Phone