Project: Forest Hill Tank Rehab & Seismic Upgrade
This project was completed on Monday, September 25, 2006. The project made seismic improvements to the Forest Hill concrete tank including: retrofit and seismic rehabilitation of the existing 300,000 gallon concrete tank; new concrete foundation, new dedicated inlet/outlet piping work; new isolation valves; retaining wall; security fencing and monitoring system, access catwalk, ladders and safety platforms on the tank; access road and site improvements including erosion control and drainage, water quality improvements (sampling, disinfection); and cathodic protection and monitoring system.
Need more information?
Contact Robert Lopez at (415) 554-3286 or via email at rlopez@sfwater.org