Project–At–A–GlanceWSIP Region Location Project Completed Project Cost |
|
Project Completed: July 2008 The adit structures function as the outlet facilities from the reservoirs and are critical links in the water supply system. These facilities contain the valves and piping used to control withdrawal of water from the reservoirs through horizontal tunnels. Leakage into the structures made access difficult and unsafe and also resulted in deterioration of equipment. The project was completed in July, 2008 coming in under budget and ahead of schedule. This project is provided in response to the Delivery Reliability level of service goal. Description | |
Contact Maureen Barry at (415) 554-3297 or via email at mbarry@sfwater.org